Major and notifiable changes after Gateway 2

How changes to a higher-risk building project are controlled once building control approval is granted, and what the change control plan in your Gateway 2 application has to say about it.

Check your Gateway 2 pack for missing documents → Free, runs in your browser, nothing uploaded.

Why it matters at Gateway 2

Change control isn't only a construction-phase issue. The change control plan is one of the documents a Gateway 2 application must include. In the BSR's review of new-build applications rejected after validation, 27% did not adequately set out how changes would be managed during construction (why Gateway 2 applications fail).

Controlled changes

Once approved, the application documents become agreed documents. Any change to them is a controlled change. Every controlled change goes in the change control log, and the affected documents are updated. Some controlled changes also need the BSR's involvement:

Changes of client, principal designer or principal contractor, and changes of contact details, must also be notified.

Examples of major changes

From the BSR's guidance. Changes to:

A material change of use, such as converting commercial units to flats, is also treated as a major change.

Examples of notifiable changes

For example, changes to:

A replacement product with a different reaction-to-fire specification may be notifiable even if it is better. One with the same or a higher class is recorded instead.

What a change application or notification needs

For each change, the BSR asks for:

For a change of client, principal designer or principal contractor, also upload the outgoing party's compliance declaration.

What the change control plan must cover

Schedule 1, paragraph 3 of SI 2023/909 requires the change control plan in the Gateway 2 application to set out:

The BSR's guidance on preparing applications adds that all advice received, including advice that was rejected, should be recorded along with who gave it. In our view, a plan written as a generic company procedure, which doesn't name the roles on this project or say how a major change would be spotted, is a weak point.

Use the list above as a manual check of your plan. The free Gateproof checker confirms that a change control plan is in the pack, alongside the other required documents. It doesn't yet check the plan's content point by point.